Plaster can be defined as lean mortar, mostly used to cover masonry surfaces (brickwork or stone works).

Mostly,we use plaster for interiorwalls of construction(houses,lintels,flooring,ceiling,etc)

They are lean mixtures of binding materials (lime or cement) with filler materials such as sand or crushed stone.

And the process of covering surfaces with plaster is called plastering.

They are specially prepared for two reasons:

1. For decoration.

2. For protection.

As a decorative finish, plasters are used to give many attractive colors and finish designs for construction and  adds to asthetics in terms of design.

In protective cover, plaster protects bricks or stones from direct destructive attacks of air, rain,moisture and harmful gases from factories or industries.

Plastering refers to the protection provided for a wall or ceiling in terms of coating the surface by laying plaster (cement plaster). Plastering is done to remove surface imperfections due to brickwork and to provide smooth surface for painting.

Different types of plastering materials are used,but cement plaster is used extensively.Some other types of plastering materials include lime plaster,clay plaster, etc.




HOW TO APPLY CEMENT PLASTER ON WALL SURFACE:

Cement plaster is usually applied in single coat or double coat.Cement plastering is commonly used as an ideal coating for the exterior and interior surface of a wall. 

Double coat plaster is applied where the thickness of the plaster is required to exceed 15 mm or when it is necessary to obtain a very fine finish. 

The process of applying a double coat cement plaster to the wall surface consists of the following steps:

Step 1 - Surface Preparation for Plastering.

Keep all the mortar joints of the wall thick, to give a good bonding to hold the plaster.

Clean all wall joints and surfaces with a wire brush, there should be no grease or grease etc. on the wall surface.

Roughen the entire wall to be plastered.

Wash the mortar joints and the entire wall to be plastered, and keep it wet for at least 6 hours before applying cement plaster.

Step 2 -  Ground work for plaster.

The dots are fixed horizontally on the wall and then vertically at a distance of about 2 metres, covering the entire wall surface.

Through the plumb-bob, check the verticality of the dots.

After fixing the dots, vertical strips of plaster, known as screeds, are formed between the dots. These serve as screw gauges to maintain plaster thickness.They hold the plasters and give uniformity of surface.

Step 3 - Applying first coat (or under coat or coat).

The ratio of cement and sand for the first coat plaster varies from 1: 3 to 1: 6.

In the case of brick masonry the thickness of the first coat plaster is in the normal 12 mm and in the case of concrete masonry the thickness varies from 9 to 15 mm.

Apply the first coat of plaster between the spaces formed by screws on the surface of the wall. This is done through trowel.

Level the surface through flat wooden floats and straight edges of wood.

After leveling, leave the first coat to set but not to dry and then thicken it with a scratch tool to key the second coat of plaster.

Step 4 -  Second coat (or finishing coat or fine coat).

The thickness of the second coat or finishing coat may vary between 2 and 3 mm.

The ratio of cement and sand for the second coat of plaster varies from 1: 4 to 1: 6.

Before applying the second coat, moisten the first coat evenly.

To eliminate joining marks,the finishing coat should be applied from starting at top towards bottom.

Care to be Taken After Plastering:

Curing the works for a minimum of 10 days  to develop strength and hardness.Write the date of plastering on the wall/ceiling with a permanent marker. (So you can track the curing days).

All mortar waste stuck to walls, floor, and MS sheet shall be cleared after the day’s work.

How to choose the right plastering material for House works?

Two major factors to be considered in any type of plaster are surface protection and material cost. If the plastering quality increases and exceeds, the cost is affected. If price is considered and the quality of the plaster is given less importance then surface safety is compromised.

It should be durable enough to sustain any climate change throughout the life span of the structure.

Plastering materials should be inexpensive and economical.

The plastering material must have excellent workability that can be applied during any weather conditions (Hot or Cold).

Points in plastering task calculations should be remembered:
The overall thickness of the plastering should be a minimum of 20 mm with two coats.
The ratios mentioned in the plastering are the volumetric ratios of cement and sand (former cement: sand = 1: 5, 1 part of cement and 5 parts of sand in a mortar).
Cement has a dry density of 1440kg/

Weight of each bag of cement = 50 kilograms or 110 pounds
Quantity of each cement bag =50 kg/1440 = 0.0348


Dry density of sand = 1600 kg/

The plastering is done in two layers (two coats): the first coat of plastering is kept with a minimum thickness of 12 mm (usually between 12–15 mm) and this coat is used as a rough coat or primary coat. 
The second coat should be kept with a thickness of 8 mm and is called the plaster finish coat or secondary coat.
Total plaster = first coat + second coat 

Steps involved in plastering calculation:

1. Find the total area of the plastered wall in sqm.
2. Consider plastering ratio and thickness.
3. Calculate the total amount of plastering in terms of volume.
4. Find the volume of cement and sand individually for both coats
5. Calculate the total volume of cement and sand required for plastering.

Considering the following values for the purpose of calculation:

The width of the wall is 10 metres.
The height of the wall is 10 metres.
The ratio of the first coat of plastering (cement: sand = 1: 5) with a thickness of 12 mm.
The ratio of plastering to secondary coat (cement: sand = 1: 3) with a thickness of 8 mm.

Step 1: Calculate the Area of Plastering

Area = width x height = 10 x 10 = 100 

Step 2: Find the Volume of Plastering 

Volume of First Coat = Area of Plastering x Thickness of Plastering

= 100 x 12mm (as 1m =1000mm)

= 100×0.012 = 1.2

Hence, Volume of First Coat of Plastering = 1.2

The volume of Second Coat = Area of Plastering x Thickness of Plastering

= 100 x 8mm (as 1m=1000 mm)

= 100×0.008 = 0.8

Hence,Volume of  Second coat of plastering = 0.8

Step 3: To find the quantities of cement and sand for first and second coat.

First coat:

The ratio of the first coat of plastering (cement: sand = 1: 5) with a thickness of 12 mm.
Total sum =1+5=6

Quantity of Cement required for First coat =

(cement/ Total sum) x Volume of First Coat = 1/6 x 1.2                           
= 0.2 ㎥     (calculation M20)

Quantity of Sand required for First coat =

(sand/ Total sum) x Volume of First Coat = 5/6 x 1.2 = 1 

Second coat:

The ratio of plastering to secondary coat (cement: sand = 1: 3) with a thickness of 8 mm.

Total sum =1+3=4

Quantity of Cement required for second coat =

(cement/ Total sum) x Volume of second Coat = 1/4x 0.8=0.2 

Quantity of Sand required for second coat =

(sand/ Total sum) x Volume of second Coat = 3/4 x 0.8 =0.6 

Before step - 4, you need to know something :

Total quantity of cement for  first + second coat as calculated above
=0.2 + 0.2 =0.4 

Total quantity of sand for  first + second coat as calculated above
=1 + 0.6 =1.6 

Volume of 1 bag of cement (50kgs) = 0.0348

For 0.4m3 = 0.4 x 50 / 0.0348
 = 574kgs = 11.4 bags

Similarly,  for Sand 1
 = 1600 kgs.

1.6 m3 = 1.6 x 1600 = 2560 kgs = 2.5 tonnes

Quantity of Water required = 627 litres. 

Step 4:To find the quantity of water required for plastering:

Amount of water to be added in mix depends upon the moisture content present in cement, sand & atmosphere.

Quantity of water = 20% of total dry material (Cement+Sand)

= 20% of (574+2560) = 0.2 x 3134 = 627 litres.

How many cement bags are required for one metre of plastering?

From above, 100= 574 kgs of cement

1 = 574/100 = 5.7 kgs

Final result:

For 100 of Wall, first & second coat of cement mortar ratio is 1:5 & 1:3.The quantity of cement, sand & water required for Plastering-then we have :-

The Quantity of cement required = 574 kgs

The Quantity of Sand (Fine aggregate) required = 2560 kgs

Quantity of Water required = 627 litres




Also Read:






2 Comments

  1. I got full of knowledge

    ReplyDelete
  2. This is a very informative resource on calculating stucco materials! The breakdown of the process, from determining the plaster area to calculating the amount of cement, sand, and water, is clear and easy to follow. This is particularly helpful for DIY enthusiasts or someone planning a small stucco project.

    The article mentions a 1:4 ratio (cement to sand) as a common starting point for stucco mixes. However, I've come across recommendations for richer mixes (like 1:3) for stronger applications. Do you have any insights on selecting the optimal cement-to-sand ratio for a stucco project? Are there specific factors, like the thickness of the stucco or desired finish, that would influence this decision?

    ReplyDelete

Post a Comment

Previous Post Next Post