Consider
Mix Ratio 1: 6 and volume of mortar is 1
cubic meter
Dry volume of mortar =
wet volume x 1.33
Dry Volume = 1 m³ x
1.33 = 1.33
Quantity
of cement = {(Dry volume of mortar x cement ratio) / (Sum of ratio)}
Quantity of cement =
(1.33 x 1) /(1+6) = 0.19 m³
Density of cement =
1440 kg /
So, Weight of cement =
1440 x 0.19 = 273.6Kg
1 bag of cement = 50 kg
So,Number of cement bags = 273.6 kg / 50 = 5.47 No.’s
Also see: Calculation of volume of 50 kg cement bag
As we know , Cement:
Sand = 1: 6
Thus,
Quantity of sand =
volume of cement x 6
Quantity of sand = 0.19 m³ x 6 = 1.14
1 m³ =
35.3147 cubic feet (CFT)
Quantity of sand = 1.14 x 35.3147 =
40.258 CFT
Density of dry sand = 1600 kg / m³